We visit a tile showroom on Satuday to look for ideas for the utility room and en-suite tiling. Mike also managed to cut a few more kitchen floor tiles yesterday. It's slow progress as the project is being balanced with other activites (like working and looking after D! Today we resume with the outdoor paving project.
The boys lay the stone in both the front and back gardens. Five tons of sand, five packs of blocks and a wacker plate are delivered. We've chosen standard blocks in a brindle colour - nothing too fancy. The front drive should be edged in charcoal coloured brick, which will be delivered at a later stage. The sand is left on the front drive along with a bundle of blocks. The remaining four sets are delivered directly into the back garden (which should save some time!). We expect to use more blocks than this, but have chosen to have them delivered in stages so that there's enough room to work. The stone is wacked into position ready for the next stage tomorrow.