Tuesday, 9 December 2008

Tuesday 09 December 2008 - Day 122

Jack and Lee arrive. They plaster the boxed in soil pipe in the kitchen, the new dividing wall between the new master bedroom/ensuite, and they make good the walls and ceiling in the new master bedroom and ensuite.

Since the new kitchen floor is cracked, Mike paints it with PVA. This seems to hold it together and reduce dust.

Mike then joins Zoe and D in Penrith, leaving the plaster to dry. We hope to re-paint and tile the kitchen before calling the builders back to fit skirting/plinths etc.