Wednesday, 18 February 2009

Wednesday 18 February 2009

The missing basin from Sinks and Taps arrived today. It was due to be delivered last week, but the original unit was damaged when it arrived to their warehouse, hence the delay.

We're also waiting for the shower tray components to arrive, so that Jim can come back to continue the install tomorrow.

The water man visits to read the meter. It's nice to be able to point him to the middle of the drive - only trouble is, he can't access the meter as it's been cemented over! Probably something to do with having a mountain of sand delivered onto the grid whilst the cement was wet... Apparently it's a common problem, he fetches a tool from the van, is able to break the concrete and reads the meter.