Monday, 24 November 2008

Monday 24 November 2008 - Day 111

Tom is here today. He works on second fix electrics in the kitchen. By the end of the day we have three zones of lights (the fourth will have to wait until more work is done on the wall cupboards) and power sockets - both on the walls and inside the cupboards (for the fridge/freezer and dishwasher).

Tom also fits the relay, that arrived today, for the underfloor heating.

Mike does more work on the alarm and routes ADSL/network cabling to the new study.

Whist admiring Tom's work, we discover that the new kitchen floor is not level. Whilst we can accept some variance, this appears to be a bit too much. It's too late to call anyone, so we text Millie with our concerns.