Darcey’s bedroom window is moved to the new rear bedroom. A couple of rows of bricks have been added to the window in Darcey’s current room before the new window is put in (as this will become a bathroom, so the sill level needs to be higher). There are not enough red bricks on site so Barry takes some out of the kitchen wall that’s due to come down. It proves an excellent match! We’re still waiting for the glass, so Darcey’s new window is single glazed for now. Mike covers the new internal brickwork with brown paper. The front window is also fitted & boarded up for the being...
The two electricians work on some of the first fix in the new part of the kitchen. They also install the new timer and control system for the heating.
The new boiler is fitted (Zoe nearly cries at the thought of having heat!). Jim also installs an outside tap for us too…
It feels like it’s been a busy day – we’ve had 9 people on site today, 10 if you count John Sheard (the boss) who visited. It make parking on the street very interesting…