After a night of stumbling around in darkness, power was re-connected today. Knowing that there was no power to the first floor lights, it was guaranteed that Darcey would wake in the middle of the night! We can now use the kitchen lights, first floor lights and are able to watch TV (it’s amazing how much we all missed Cbeebies!).
The kitchen brickwork continues – the outer walls grow taller. Rain has slowed progress slightly, it’s also washed away some of the mortar in the new red-brick wall. The plan is to let the existing mortar dry, before re-pointing the missing bits.
Blocks are moved onto the scaffolding/garage roof in order for first floor block work to commence on Monday.
Inside acro props hold up the garage roof. The top of the garage wall has been removed. It’s strange to stand inside the garage & see light streaming in through around the edges! The kitchen and utility room are still to go through this process. We believe that this will start the de-commissioning of the kitchen, a part of the build that we’ve not been looking forward to. The kitchen coving finally fell down today.
The second skip was collected and a new one has been placed on the drive. Next to the empty skip sits another delivery of sand. There is now no longer any room for one of our cars on the drive/garden. So far the neighbours have been very accommodating (the build seems to be providing the local kids with much entertainment!), so we hope that having vehicles on the street isn’t going to cause too much chaos.





1 comment:
Why didn't you use Mike's generator when you lost the power to the lights? ;-)
Bill.